THE DEVELOPMENT
What happened
On September 25, Cipher reported contracted revenue exceeding $9 billion, including approximately $5.2 billion from an additional decade committed by an unnamed AI lab. Delivery is phased from late 2026 into early 2027; rent begins as individual halls are delivered.
Cipher bears the first $359.3 million above the original construction budget. Half of costs beyond that threshold are reimbursable through additional rent over the aggregate term. These commitments represent future revenue, not cash already collected.
PREMIA VIEW
What this means for operators and investors
Buyers should value the cash remaining after construction, financing and ongoing investment. A longer contract can improve visibility while leaving substantial funding requirements upfront.
WHAT REMAINS UNCERTAIN
Final costs, delivery performance and the unnamed lab’s credit protections.
DECISION QUESTIONS
Three questions stakeholders should answer now.
- 01How much cash is needed before rent starts?
- 02Who absorbs further overruns?
- 03What protects collections if the tenant cannot perform?
WHAT TO WATCH
What to watch next
First rent commencement, completed halls and updated construction spending.